a16z Argues Flexible Data Centers Could Bypass Texas Grid Queue
a16z's Ryan McEntush argues that data centers agreeing to curtail power during peak hours can connect to congested grids sooner. He cites Texas's queue growing to 474 GW, about 90% of it data centers, and estimates 100 GW of flexible capacity could be added without new plants.
Original post · 1 min read
Right: New data centers that agree to cut back during peak hours can skip the wait for more capacity. US grids could add 100 GW of them without building a single new plant.
a16z's @rmcentush on how flexible data centers get onto the grid sooner: a16z.news/p/why-texas-is-making-data-centers
Ryan McEntush @rmcentushWhy Texas Is Making Data Centers Wait — At the end of 2024, Texas’ grid operator had 63 GW of large new customers in its queue. By this June, that figure reached 474 GW, more than five times record peak demand, about 90% of it data centers.